Segment C (C1 & C2)

Approximately 10 miles of 84-inch diameter pipeline.

The bid deadline for Segment C ended on July 30, 2020, at 2PM. Please see CIVCAST for further details.  Once contractors for Segment C have been selected by the Board, additional information will be made available online.

These maps are for illustration purposes only.  Lines are not to scale.

Drone Footage Segment C – For information only 6-2-2020

Click the gear icon on the player below to control the video playback speed.

Segment C1 Location: Westfield Village to Highway 6

  • Pipeline Diameter: 84″
  • 5.2 Miles in length

Anticipated Construction Program Schedule

DESIGN

Spring 2020

BID

Summer 2020 – Fall 2020

CONSTRUCTION

Early 2021 – Spring 2024

Design Consultant: Freese and Nichols, Inc.

Contractor: S.J. Louis Construction

PDF Map: SWSP – Segment C1

Contractor Notice to Proceed: September 2020

Project Completion: (To be determined) ) – Note: a detailed construction schedule is currently under development

Dates are subject to change

SWSP - Segment C1

Segment C2 Location: Highway 6 to Brittmoore Road

  • Pipeline Diameter: 84″
  • 4.9 miles in length

Anticipated Construction Program Schedule

DESIGN

Spring 2020

BID

Summer 2020 – Fall 2020

CONSTRUCTION

Early 2021 – Late Spring 2024

Design Consultant: Freese and Nichols, Inc.

Contractor: Harper Brothers Construction

PDF Map: SWSP – Segment C2

Contractor Notice to Proceed: September 2020

Project Completion: (To be determined) – Note: a detailed construction schedule is currently under development

Dates are subject to change

SWSP - Segment C2