Segment 3 (CenterPoint Corridor)
Approximately 13.8 miles of 42-inch-diameter pipeline.
The Segment 3 waterline is a 42-inch waterline that extends approximately 13.8 miles from Segment C (84-inch Waterline) near Brittmoore Road to the NFBWA Bellaire Pump Station along CenterPoint Energy (CPE) easements and some private easements.
Segment 3 will provide water to both NFBWA and WHCRWA customers via the Bellaire Pump Station.
Segment 3 is currently planned to be constructed in six separate construction packages. Per the agreement with CPE, waterline construction within the CPE corridor has to start construction by February 27, 2020.
Although the agreement does not specify the duration to construct the waterline through the entire corridor, construction activities are anticipated to finalize by the first quarter of 2023 The construction projects will be advertised in the Houston Business Journal and available on Civcast online bidding website. These projects will not require pre-qualification and consequently will be open to any contractor.
SEG3-A1
- Pipeline Diameter: 42″
- 2.7 miles in length
Anticipated Construction Program Schedule
DESIGN
Fall 2020
BID
Summer – Winter 2021
CONSTRUCTION
Winter 2021 – Spring 2023
Design Consultant: Binkley & Barfield, Inc. (BBI)
Contractor: (To be determined)
PDF Map: SWSP – Segment 3 A-1
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change

SEG3-A2
- Pipeline Diameter: 42″
- 2.7 miles in length
Anticipated Construction Program Schedule
DESIGN
Fall 2020
BID
Summer — Fall 2021
CONSTRUCTION
Fall 2021 – Fall 2023
Design Consultant: Kimley-Horn
Contractor: (To be determined)
PDF Map: SWSP – Segment 3 A-2
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change

SEG3-A3
- Pipeline Diameter: 42″
- 1.7 miles in length
Anticipated Construction Program Schedule
DESIGN
Fall 2020
BID
Summer 2021
CONSTRUCTION
Fall 2021 – Early 2023
Design Consultant: Freese and Nichols, Inc. (FNI)
Contractor: (To be determined)
PDF Map: SWSP – Segment 3 A-3
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change

SEG3-A4
- Pipeline Diameter: 42″
- 2 miles in length
Anticipated Construction Program Schedule
DESIGN
Summer 2019
BID
Winter 2019
CONSTRUCTION
Late 2019 – Early 2021
Design Consultant: Costello
Contractor: Garney Construction
PDF Map: SWSP – Segment 3 A-4
Contractor Notice to Proceed: 12/12/2019
Project Completion: Early 2021
Dates are subject to change

SEG3-A5
- Pipeline Diameter: 42″
- 1.9 miles in length
Anticipated Construction Program Schedule
DESIGN
Fall 2020
BID
Fall 2021
CONSTRUCTION
Late 2021 – Early 2023
Design Consultant: Huitt-Zollars,Inc.
Contractor: (To be determined)
PDF Map: SWSP – Segment 3 A-5
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change

SEG3-B1
- Pipeline Diameter: 42″
- 2.9 miles in length
Anticipated Construction Program Schedule
DESIGN
Ends Fall 2020
BID
Summer 2021
CONSTRUCTION
Fall 2021– Summer 2023
Design Consultant: BGE, Inc. (BGE)
Contractor: (To be determined)
PDF Map: SWSP – Segment 3 B-1
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change
