Segment 3 (CenterPoint Corridor)

Approximately 13.8 miles of 42-inch-diameter pipeline.

The Segment 3 waterline is a 42-inch waterline that extends approximately 13.8 miles from Segment C (84-inch Waterline) near Brittmoore Rd. to the NFBWA Bellaire Pump Station (PS) along CenterPoint Energy (CPE) easements and some private easements. Segment 3 will provide water to both NFBWA and WHCRWA customers via the Bellaire PS. Currently, Segment 3 is planned to be constructed in six separate construction packages. Per the agreement with CPE, waterline construction within the CPE corridor must begin by February 27, 2020. Although the agreement does not specify the duration to construct the waterline through the entire corridor, construction activities are anticipated to finalize by the fourth quarter of 2021.

SEG3-A1

  • Pipeline Diameter: 42″

Anticipated Construction Program Schedule

DESIGN

Ends Q2/2020

BID

Q3/2020

CONSTRUCTION

Q4/2020 – Q4/2021

Design Consultant: Costello

Contractor: (To be posted)

PDF Map: SWSP – Segment 3 A-1

Contractor Notice to Proceed: (To be posted)

Project Completion: (To be posted)

Dates are subject to change

SWSP - Segment 3 A-1

SEG3-A2

  • Pipeline Diameter: 42″

Anticipated Construction Program Schedule

DESIGN

Ends Q4/2019

BID

Q1/2020

CONSTRUCTION

Q2/2020 – Q3/2021

Design Consultant: Costello

Contractor: (To be posted)

PDF Map: SWSP – Segment 3 A-2

Contractor Notice to Proceed: (To be posted)

Project Completion: (To be posted)

Dates are subject to change

SWSP - Segment 3 A-2

SEG3-A3

  • Pipeline Diameter: 42″

Anticipated Construction Program Schedule

DESIGN

Ends Q4/2019

BID

Q1/2020

CONSTRUCTION

Q2/2020 – Q3/2021

Design Consultant: Costello

Contractor: (To be posted)

PDF Map: SWSP – Segment 3 A-3

Contractor Notice to Proceed: (To be posted)

Project Completion: (To be posted)

Dates are subject to change

SWSP - Segment 3 A-3

SEG3-A4

  • Pipeline Diameter: 42″

Anticipated Construction Program Schedule

DESIGN

Ended Q3/2019

BID

Q4/2019

CONSTRUCTION

Q1/2020 – Q1/2021

Design Consultant: Costello

Contractor: Garney Construction

PDF Map: SWSP – Segment 3 A-4

Contractor Notice to Proceed: (To be posted)

Project Completion: (To be posted)

Dates are subject to change

SWSP - Segment 3 A-4

SEG3-A5

  • Pipeline Diameter: 42″

Anticipated Construction Program Schedule

DESIGN

Ends Q4/2019

BID

Q1/2020

CONSTRUCTION

Q2/2020 – Q3/2021

Design Consultant: Costello

Contractor: (To be posted)

PDF Map: SWSP – Segment 3 A-5

Contractor Notice to Proceed: (To be posted)

Project Completion: (To be posted)

Dates are subject to change

SWSP - Segment 3 A-5

SEG3-B1

  • Pipeline Diameter: 42″

Anticipated Construction Program Schedule

DESIGN

Ends Q4/2019

BID

Q3/2020

CONSTRUCTION

Q4/2020 – Q4/2021

Design Consultant: Costello

Contractor: (To be posted)

PDF Map: SWSP – Segment 3 B-1

Contractor Notice to Proceed: (To be posted)

Project Completion: (To be posted)

Dates are subject to change

SWSP - Segment 3 B-1