Segment 3 (CenterPoint Corridor)

Approximately 13.8 miles of 42-inch-diameter pipeline.

The Segment 3 waterline is a 42-inch waterline that extends approximately 13.8 miles from Segment C (84-inch Waterline) near Brittmoore Road to the NFBWA Bellaire Pump Station along CenterPoint Energy (CPE) easements and some private easements.

Segment 3 will provide water to both NFBWA and WHCRWA customers via the Bellaire Pump Station.

Segment 3 is currently planned to be constructed in six separate construction packages. Per the agreement with CPE, waterline construction within the CPE corridor has to start construction by February 27, 2020.

Although the agreement does not specify the duration to construct the waterline through the entire corridor, construction activities are anticipated to finalize by the first quarter of 2023 The construction projects will be advertised in the Houston Business Journal and available on Civcast online bidding website. These projects will not require pre-qualification and consequently will be open to any contractor.

SEG3-A1

  • Pipeline Diameter: 42″
  • 2.7 miles in length

Anticipated Construction Program Schedule

DESIGN

Ended Summer 2020

BID

Spring 2021

CONSTRUCTION

Fall 2021 – Fall 2022

Design Consultant: Binkley & Barfield, Inc. (BBI)

Contractor: R Construction

PDF Map: SWSP – Segment 3 A-1

Contractor Notice to Proceed: August 2021

Project Completion: Fall 2022

SWSP - Segment 3 A-1

SEG3-A2

  • Pipeline Diameter: 42″
  • 2.7 miles in length

Anticipated Construction Program Schedule

DESIGN

Ended Summer 2020

BID

Spring 2021

CONSTRUCTION

Summer 2021 – Late Fall 2022

Design Consultant: Kimley-Horn

Contractor: E.P. Brady, LTD

PDF Map: SWSP – Segment 3 A-2

Contractor Notice to Proceed: July 2021

Project Completion: Late Fall 2022

Dates are subject to change

SWSP - Segment 3 A-2

SEG3-A3

  • Pipeline Diameter: 42″
  • 1.7 miles in length

Anticipated Construction Program Schedule

DESIGN

Ended Spring 2020

BID

Summer 2021

CONSTRUCTION

Fall 2021 – Late Fall 2022

Design Consultant: Freese and Nichols, Inc. (FNI)

Contractor: Main Lane Industries, Ltd.

PDF Map: SWSP – Segment 3 A-3

Contractor Notice to Proceed: September 2021

Project Completion: Late Fall 2022

Dates are subject to change

SWSP - Segment 3 A-3

SEG3-A4

  • Pipeline Diameter: 42″
  • 2 miles in length

Anticipated Construction Program Schedule

DESIGN

Ended Fall 2019

BID

Winter 2019

CONSTRUCTION

Construction Complete

Design Consultant: Costello

Contractor: Garney Construction

PDF Map: SWSP – Segment 3 A-4

Contractor Notice to Proceed: 12/12/2019

Project Completion: Early 2021

Dates are subject to change

SWSP - Segment 3 A-4

SEG3-A5

  • Pipeline Diameter: 42″
  • 1.9 miles in length

Anticipated Construction Program Schedule

DESIGN

Ended Spring 2021

BID

Spring 2022

CONSTRUCTION

Summer 2022 – Summer 2023

Design Consultant: Huitt-Zollars,Inc.

Contractor: (To be determined)

PDF Map: SWSP – Segment 3 A-5

Contractor Notice to Proceed: (To be determined)

Project Completion: (To be determined)

Dates are subject to change

SWSP - Segment 3 A-5

SEG3-B1

  • Pipeline Diameter: 42″
  • 2.9 miles in length

Anticipated Construction Program Schedule

DESIGN

Winter 2021

BID

Fall 2022

CONSTRUCTION

Winter 2022– Summer 2024

Design Consultant: BGE, Inc. (BGE)

Contractor: (To be determined)

PDF Map: SWSP – Segment 3 B-1

Contractor Notice to Proceed: (To be determined)

Project Completion: (To be determined)

Dates are subject to change

SWSP - Segment 3 B-1